Development update
Underwriting basis
Generic 100-key hotel model with current operating and capital assumptions.
Room program
100 keys: 50 Economy Plus with en-suite bathrooms and 50 Economy with shared bathrooms.
Model connection
Room count, room mix, land acres, loan and bridge assumptions pull from the pro forma.
Investor guardrail
Prior return claims were removed. IRR and exit metrics stay off until STAR/operating assumptions are refreshed.
Project cost snapshot — 100-key model
Total project uses (financing model)$7.15M
Hard construction budget$4.58M
Owner direct & FF&E/OSE$0.72M
Bridge interest reserve$109K
Construction loan @ 70% LTC$5.00M
Equity required @ 30%$2.14M
Construction + FF&E/OSE control total$7.46M
Keys100
Room mix50 Economy Plus / 50 Economy
Gross building area18,151 SF
The $7.15M project-use total is the current financing model number. The $7.46M construction + FF&E/OSE control total is kept visible as a diligence check until scope, contingency and procurement reconciliation are final.
Architecture & renders
Current renders. Floor plans and the full 3D model can be added here — drop those files in and they'll slot into this section.